Media reports that the government is finally weighing whether to pull the plug on the Monju fast-breeder reactor in Tsuruga, Fukui Prefecture, due to the massive cost needed to restart the long-dormant facility, should come as no surprise. Once touted as a "dream reactor" for an energy-scarce country that produces more plutonium than it consumes as fuel, Monju has been a nightmare for national nuclear power policy for the past two decades. The sole prototype reactor for this kind of technology has been in operation a mere 250 days since it first reached criticality in 1994. It has mostly been offline since a 1995 sodium coolant leak and fire. Its government-backed operator has been declared unfit by nuclear power regulators to run the trouble-prone reactor, and the education and science ministry, in charge of the project, has not been able to find a viable solution.

More than ¥1 trillion in taxpayer money has so far been spent on Monju, and maintenance alone costs ¥20 billion a year. Restarting the reactor under the Nuclear Regulation Authority's new safety standards would cost another several hundred billion yen, including the expense of replacing its long-unused fuel as well as its aging components — though there would still be no guarantee that it would complete its mission of commercializing fast-breeder reactor technology.

The Abe administration may think that writing off the ill-fated costly project, even with the projected ¥300 billion cost of decommissioning the facility over 30 years, will help win more public support for its policy of seeking to reactivate the nation's conventional reactors — most of which remain idled in the wake of the 2011 meltdowns at Tokyo Electric Power's Fukushima No. 1 plant — once they've cleared the NRA screening. Public concerns over the safety of nuclear energy remain strong after the Fukushima disaster, with media surveys showing a large portion of respondents still opposed putting the idled reactors back online.